HISTORY
      In the late 70's the Environmental Protection Division felt there was a need to mandate the improvement of wastewater treatment in the Upper Ocmulgee River Basin due to the environmental conditions affecting Jackson Lake. Recognizing this need, the City of Covington and the Newton County Water & Sewerage Authority (NCWSA) undertook a joint venture project resulting in the construction of the existing 4.8 million gallon per day Land Application Facility. The engineering firm of Welker & Associates of Marietta, GA. planned and designed the project that was completed in 1985 at a cost of nearly $7 million dollars.
DESCRIPTION
      The 864-acre land application facility receives effluent from two secondary activated sludge plants. A 3.0 million gallon per day plant operated by the City of Covington and a 1.8 million gallon per day plant operated by the NCWSA both pump their treated wastewater to a storage pond at the land application site. This pond is 18 acres in size, has a capacity of 72 million gallons, and is home to a variety of fish, snakes, turtles, ducks and other wildlife.
      The irrigation system consists of 54 miles of underground pipe with nearly 5000 sprinklers. It is distributed throughout a forested system of pines and hardwoods. It is designed with eight sprayfields that comprise a total of 617 irrigated acres. Irrigation lines are 85 feet apart and sprinklers are spaced every 60 feet on the lines. Drain valves are provided on each line to prevent freeze damage.
      Required buffer zones are 300 feet from residential dwellings, 150 feet from public roads, and 100 feet from any surface waters. With these minimum requirements, the land application process should
virtually go unnoticed to the public and its neighbors.
MONITORING
     The Georgia Environmental Protection Division issued and renews the permit for the Covington/Newton County Land Application Facility. According to this permit, certain pretreatment and monitoring requirements must be met. It is important that the secondary plants send a quality effluent to the storage pond for irrigation. An industrial pretreatment program is also required to monitor industrial discharge strengths into the sewerage collection system. Within the Land Application Facility, routine monitoring takes place on the soil, groundwater quality, and upstream and downstream points of Dried Indian Creek. Monitoring data and irrigation amounts are all submitted to the Georgia E.P.D. in a monthly report.
After years of success, the Environmental Protection Division strongly encourages the construction of land treatment systems over direct stream discharges.
OPERATION AND MAINTENANCE
      One of the eight designed sprayfields can be irrigated for up to 12 hours per day. The field is then allowed to dry and re-aerate 6-7 days before being irrigated again. A maximum of 2.25 inches of effluent is allowed to be sprayed over each field in a seven day period.
     As the treated wastewater is irrigated, the trees and vegetation take up the available nutrients contained within the irrigated water. Specifically, these nutrients are nitrogen and phosphorous, which are two of the three basic components in a commercial fertilizer. After the plants use these nutrients for growth, the soil then acts as a filtering device for the remaining nutrients.When this process is complete, a quality effluent is delivered to the groundwater table.
      Routine maintenance is required to ensure proper operation. Keeping lateral lines clear of windblown and fallen debris, and mowing the vegetative cover are necessary to allow quick inspections and access to the irrigation system. Maintenance of the irrigation site also includes cleaning sprinkler nozzles, pipe repair, keeping a sufficient ground cover crop, and controlling any erosion that may occur.
     Maintenance requires the use of low ground pressure equipment and must be scheduled according to the soil moisture conditions in each field.
COSTS
      The Covington/Newton County Land Application Facility has operated with relatively low operations and maintenance costs. Though the initial investment costs were significant, the O&M costs associated with tertiary land treatment are much lower than the more intensive physical and chemical treatments required for a stream discharge. Of the annual budget amount, approximately 50% is applied toward salaries and benefits. Personnel is made up of four employees : two operators, one equipment operator, and one manager. Utilities (pumping costs), maintenance, supplies and materials make up the remaining 50% of the budget.
REVENUES
      Land application also offers the benefit of harvesting a byproduct crop. By using a forested system for the uptake of nutrients, periodic harvesting is necessary to maintain an efficient uptake of nutrients.As these forested cells reach their efficiency maximum the timber is then sold and harvested. Revenue received from this sale of timber is deposited into an account designated for capital improvements at the Land Application Facility.
     Significant purchases of capital items, such as tractors, have all been purchased through this account.
After the timber is harvested, the site is then replanted. A management plan has been established in order to maintain a healthy balance between mature and younger stands of timber.

FOR MORE INFORMATION
PLEASE CONTACT :

CITY OF COVINGTON
LAND APPLICATION FACILITY
11085 FLAT SHOALS ROAD
COVINGTON, GA. 30016
770/385-2048 (OFFICE)
770/385-6828 (FAX)